Columbia Gas Transmission, LLC
FERC Gas Tariff
Third Revised Volume No. 1

Original Sheet No. 169

                                       FSS-M RATE SCHEDULE
                    FIRM STORAGE SERVICE WITH MARKET-BASED RATES (cont'd)

        Any request by Shipper for permission to make withdrawals in excess of its maximum monthly 
 net withdrawal limit must be submitted to Transporter electronically through Transporter's EBB at 
 least 24 hours in advance.  Transporter will grant the request if:  (i) there is additional 
 withdrawal flexibility during the time period of the request, in accordance with Section 7 
 (Capacity Allocation) of the General Terms and Conditions; and (ii) Transporter, in its 
 reasonable discretion, can operationally accommodate the request(s).  If Shipper exceeds the 
 maximum monthly net withdrawal limit during any of the Months November through March, Shipper's 
 maximum monthly net withdrawal quantity for the succeeding Month will be reduced by an amount 
 equal to the excess quantities withdrawn during the excess withdrawal Month.  Shipper's 
 withdrawals during the Months April through October will not be subject to maximum or minimum 
 withdrawal limits; provided, however, that Shipper's withdrawals during that period will be 
 subject to the limitations of Shipper's SCQ levels.  

        (d)    Shipper's maximum storage inventory on April 1 must not exceed 25% of its SCQ.  
 Shipper's maximum storage inventory on February 1 must not exceed 65% of its SCQ.  Quantities in 
 excess of 25% of Shipper's SCQ will not be carried over beyond April 1.

        (e)    Quantities taken on any Day by Shipper under all Service Agreements with 
 Transporter held by Shipper and by other shippers delivering to Shipper, but not nominated by 
 Shipper on such Day, will be deemed to be withdrawals from FSS-M storage for Shipper under this 
 Rate Schedule.  

        (f)    Shipper may withdraw from storage, on an interruptible basis, quantities in excess 
 of Shipper's MDWQ.  These interruptible withdrawals will have the priority set forth in Section 7 
 (Capacity Allocation) of the General Terms and Conditions and will be subject to interruption as 
 set forth in Section 16 (Interruptions of Service) of the General Terms and Conditions.

        (g)    Transporter may waive a Shipper's default of any of the limitations set forth in 
 this Section that has already occurred. In addition, Transporter may waive a Shipper's default of 
 these limitations in advance, provided that the waiver is required to address a specific, 
 temporary, operational problem. Any waiver granted pursuant to this Section must be granted in a 
 non-discriminatory manner on case-by-case basis.

5.      RECEIPT AND DELIVERY POINTS  

        Service under this Rate Schedule will not be subject to the flexible receipt and delivery 
 point provisions of Section 11 (Flexible Primary and Secondary Receipt and Delivery Points) of 
 the General Terms and Conditions.  The point of delivery for all gas tendered to Transporter for 
 storage under this Rate Schedule will be designated in transportation Service Agreement(s) with 
 Transporter as "FSS-M Storage."  The point of receipt for all gas delivered by Transporter to 
 Shipper hereunder will be designated in Shipper's Service Agreements with Transporter as "FSS-M 
 Storage."

Issued by: Claire A. Burum, SVP Regulatory Affairs
Issued on: March 25, 2009                     Effective on: April 22, 2009
Filed to comply with order of the Federal Energy Regulatory Commission, Docket 
No. CP08-431-000, issued March 19, 2009, 26 FERC ¶ 61,237