                                              IPP RATE SCHEDULE
                                      INTERRUPTIBLE PAPER POOLS (Cont'd)

        (d)      In the event that supplies exceed nominations for a given pool under this Rate Schedule, 
 Shipper shall identify through Transporter's EBB the priorities of flow so as to enable Transporter to reduce 
 supplies to match the market demand.  In the event that nominations exceed supplies for a given pool under 
 this Rate Schedule, Transporter shall reject any nominations against that pool that have not been confirmed by 
 Shipper.

        (e)      Any differences between confirmed nominations and actual receipt quantities shall be held as an 
 operational imbalance under Shipper's IPP Service Agreement.  Such an imbalance shall not exceed two percent 
 of Shipper's aggregate nominations for the Month.  To maintain a concurrent balance between receipts and 
 deliveries, Transporter may monitor and adjust confirmed nominations in accordance with the provisions of 
 Section 6 (Nominating, Scheduling, and Monitoring) of the General Terms and Conditions.  Shipper shall correct 
 operational imbalances at the first available opportunity, but in no event later than the last day of the 
 month in which Shipper is notified of its imbalance status for the immediately preceding month, by tendering a 
 nomination to Transporter in accordance with Sections 6.2(j) and 6.2(k) of the General Terms and Conditions.  

4.      RATE

        No rate will be charged for service under this Rate Schedule.  Transporter shall continue to charge any 
 applicable gathering service charge for those pool quantities from sources to which the gathering service 
 applies.  Transporter reserves the right to file pursuant to Section 4 of the Natural Gas Act to implement 
 charges to recover any and all costs of providing service under this Rate Schedule.  Before Transporter 
 implements such a charge, Shipper shall have the right to cancel its IPP Service Agreements that are subject 
 to that charge.

5.      PENALTIES

        (a)      If Shipper fails to interrupt service as directed by Transporter pursuant to Section 16 
 (Interruptions of Service) of the General Terms and Conditions and takes gas from or tenders gas to 
 Transporter in excess of 103 percent of the lowered Scheduled Daily Receipt or Delivery Quantity (Lowered 
 Quantity) set by Transporter's interruption order, Shipper shall be assessed and pay penalties of $5.00 per 
 Dth on the first three percent of quantities taken or tendered in excess of its Lowered Quantity, and $10.00 
 per Dth for quantities taken or tendered in excess of 103 percent of its Lowered Quantity. 

        (b)      If Shipper fails to comply with an operational flow order issued by Transporter pursuant to 
 Section 17 (Operational Flow Orders) of the General Terms and Conditions, a penalty of $5.00 per Dth per day 
 shall be assessed to Shipper for all quantities in violation of that operational flow order.  

6.      GENERAL TERMS AND CONDITIONS

        All of the General Terms and Conditions are applicable to this Rate Schedule and are hereby made a part 
 hereof, with the exception of Sections 4, 14, 19.1, 19.2 19.4, and 33 through 46.

Issued by: Claire A. Burum, SVP Regulatory Affairs