Previous  Next  Search
Columbia Gas Transmission, LLC
FERC Gas Tariff
Third Revised Volume No. 1

First Revised Sheet No. 117
Superseding
Original Sheet No. 117

                                              OPT RATE SCHEDULE
                                OFF-PEAK FIRM TRANSPORTATION SERVICE (Cont'd)

                 (1)      A day of interruption shall be deducted from Shipper's number of remaining days of 
        allowable interruption for each Day upon which Shipper is allocated a level of capacity equivalent to 
        less than 50 percent of Shipper's nominated quantity.  

                 (2)      A half day of interruption shall be deemed to have occurred and shall be deducted from 
        Shipper's number of remaining days of allowable interruption on any Day on which Transporter notifies 
        Shipper that Transporter will be able to render service at a level equal to or greater than 50 percent, 
        but less than 100 percent, of Shipper's nominated quantity; provided, however, that a full day of 
        interruption shall be deducted from Shipper's number of remaining days of allowable interruption if, on 
        any Day on which Transporter makes less than Shipper's full Transportation Demand available, Shipper 
        actually utilizes less than 50 percent of its nominated quantity.  

                 (3)      A day of interruption shall be deducted from Shipper's number of remaining days of 
        allowable interruption for each Day Shipper does not submit a nomination for this service following 
        notification by Transporter twenty-four (24) hours in advance of the Gas Day that Transporter will be 
        unable to render service up to the level of Transportation Demand specified in the OPT Service 
        Agreement.

  (e)            If Transporter provides advance notice that service under this Rate Schedule will not be 
  available, Shipper will not be entitled to a day of interruption if Shipper nominates and is allocated its 
  full Transportation Demand.  Days of interruption when Shipper nominates and is allocated less than its full 
  Transportation Demand shall be determined in accordance with Section 3 (d), above.

        (f)      If circumstances beyond Transporter's control mandate interruptions of service in excess of the 
 number of days of allowable interruption stated in Shipper's OPT Service Agreement, Transporter shall provide 
 a demand charge credit to Shipper for each such additional day of interruption.  That credit shall constitute 
 Shipper's exclusive remedy for any such interruptions.

4.      RATE

        (a)      The charges to be paid by Shipper, as set forth in paragraph (b) below, shall be no higher than 
 the applicable total effective maximum charges and no lower than the applicable total effective minimum 
 charges set forth in the currently effective Sheet No. 27 of this Tariff, unless otherwise mutually agreed to 
 by Transporter and Shipper with respect to the charges identified in Section 4(b) below.

        (b)      For all service rendered under this Rate Schedule, Shipper each month shall pay Transporter the 
 charges set forth below, unless otherwise mutually agreed to by Transporter and Shipper with respect to the 
 charges identified in Section 4(b) below and specified in Shipper's OPT Service Agreement.

                 (1)      Reservation Charge.  The maximum Reservation Charge for each Month, assessed on each 
        Dth of Transportation Demand specified in Shipper's OPT Service Agreement.  

                 (2)      Commodity Charge.  The maximum Commodity Charge per Dth of gas actually delivered each 
        Day during the Month to or for the account of Shipper.

                 (3)      Overrun Charge.  The applicable Overrun Charge per Dth of gas actually delivered on 
        any Day during the Month in excess of Shipper's Transportation Demand.

                 (4)      Surcharges.  The surcharges applicable to this Rate Schedule.

                 (5)      Processing Charge.  If applicable under Section 25.3 of the General Terms and 
        Conditions, the Processing Charge per Dth of gas processed by Transporter in its gas processing 
        facilities.

Issued by: Claire A. Burum, SVP Regulatory Affairs
Issued on: March 11, 2009                     Effective on: April 10, 2009
Filed to comply with order of the Federal Energy Regulatory Commission, Docket 
No. RP09-289-000, issued February 24, 2009, 26 FERC ¶ 61,168
Previous  Next  Search